WORK PACKAGE 1: Prerequisite for data exchange
Prerequisite for data exchange: 01.01.2019 - 30.04.2019
- Scientific presentation of relevant eHealth standards for documentation and communication tasks in diabetic foot syndrome care
- Presentation of a data protection concept
WORK PACKAGE 2: Workflow analysis
Workflow analysis :01.01.2019-30.04.2019
- Representation of the treatment and care processes with BPMN
- Tabular recording of the documentation
- Comparative analysis of the documentation with guidelines and expert standards of the professional associations
WORK PACKAGE 3: Target conceptualisation
Target conceptualisation: 01.05.2019-31.07.2019
1.
- Representation of the treatment and supply processes with BPMN
- Determination of the documentation content
- Determination of the data set for the electronic communication of the stakeholders
2.
- Adaptation of the TARGET process with the help of the findings of WP 8
- Concept for the treatment of diabetic foot syndrome with the help of iFoot
- Business model for iFoot
WORK PACKAGE 3: Semantics
Semantics: 01.06.2019 - 31.08.2019
- Semantic coding of the data set
- Determination of the coding result with the highest equivalence to the original concept
- Documentation according to ISO DTS 21564
WORK PACKAGE 3: Implementation Guide
Implementation Guide: 01.08.2019 - 31.12.2019
1.
- Definition of the use cases
- Basic Guide
2.
- Implementation Guide "iFoot based on FHIR "
- Semantic codes as value sets
WORK PACKAGE 6: Development of the specific software
Development of the special software: 01.01.2020 - 28.02.2021
- Provision of iFoot software with the option of different language settings for patients
- iFoot software integrated warning system for patients
- 3D visualisation
WORK PACKAGE 7: Development of the smart bandage
Development of the intelligent federation: 01.08.2019 - 31.07.2020
- Provision of the iFoot bandage
- Functionality of iFoot bandage and iFoot software
WORK PACKAGE 8: Implementation phase / Pilot study
Implementation phase/pilot study: 01.02.2020 - 31.07.2021
1.
- Ethics application / Defined evaluation points
- Defined cost/benefit indicators and surrogate parameters
- Pre-final questionnaires for the involved stakeholders
2.
- First Softwareupdate
3.
- Second Softwareupdate
4.
- Completed implementation phase
- Documented evaluation
WORK PACKAGE 9: Cost-benefit analysis
Cost-benefit analysis: 01.08.2021 - 31.12.2021
- Cost-benefit analysis / Economic and qualitative comparison between intervention and control group
WORK PACKAGE 10: Project management
Project management: 01.01.2019 - 31.12.2021
- Successful completion of the project
WORK PACKAGE 11: Quality Management & Risk Management
Quality management & risk management: 01.01.2019 - 31.12.2021
- Existence of comprehensible documentation of the results
WORK PACKAGE 12: Public Relations, Sustainability and Transfer
Public relations, sustainability and transfer: 01.01.2019 - 31.12.2021
- Public Relations
- Publications and scientific publications